Preparing The Concrete Flooring Base For Hoist Installations

Preparing The Concrete Flooring Base For Hoist Installations 1

If the concrete floor does not meet the required specifications, comply with WorkSafe. i.e thickness of the concrete and MPA (Mega Pascall) strength of the concrete.

 

The following should be undertaken:

 

A) The two points where the posts will be positioned must be strengthened, the concrete needs to be cut, and a new base poured, normally 1m by 1m by

a minimum 600mm in-depth, the top of this new pad must be flat and level with the rest of the workshop floor.

B) A minimum of 35 days should be allowed for the concrete to cure.

Note: The absolute minimum concrete thickness must be 150MM 32MPA
We the Team at Classic Lift Australia always discuss these very important factors with the customers and we advise accordingly